MCA-Nepal Begins Building 90-km New Butwal–New Damauli 400 kV Line; 250 Towers Planned

MCA-Nepal has started building the 90-km New Butwal–New Damauli 400 kV double-circuit transmission line under the MCC Nepal Compact from Tanahun and Palpa. The section will have 250 towers across four districts.

Artha Kendra Artha Kendra
Sat, Nov 21, 2026 11:26 AM
—
Font
MCA-Nepal Begins Building 90-km New Butwal–New Damauli 400 kV Line; 250 Towers Planned

Kathmandu. The Millennium Challenge Account Nepal (MCA-Nepal) has begun building the 400 kV double-circuit transmission line linking the New Butwal Substation and the New Damauli Substation. According to MCA-Nepal, work on the line started in Tanahun and Palpa districts on Friday, November 20.

The New Butwal–New Damauli section is 90 km long, part of the roughly 315 km of transmission lines being built under the Millennium Challenge Corporation (MCC) Nepal Compact. It will pass through four districts: Tanahun, Palpa, Nawalparasi (Bardaghat Susta East) and Nawalparasi (Bardaghat Susta West).

MCA-Nepal said a total of 250 transmission towers will be built in these districts.

Waiba–Salasar JV Is the Contractor

According to MCA-Nepal's contract award notice, the contract for this section (Lot 3) went to Waiba–Salasar JV. The contract was signed in August 2025.

The contract is worth $74.95 million excluding VAT. Adding a provisional sum of about $2.07 million, which MCA-Nepal can use at its discretion, brings the total to about $77 million. The contractor has 42 months from the commencement date to complete the line.

A 315-km Network and Three Substations

The government has designated the MCC Nepal Compact's Electricity Transmission Project a national pride project. It covers about 315 km of 400 kV transmission lines in five sections: Lapsiphedi–Ratmate, Ratmate–New Hetauda, Ratmate–New Damauli, New Damauli–New Butwal and New Butwal–Indian border.

The project also includes three 400 kV substations at Ratmate in Nuwakot, New Damauli in Tanahun and New Butwal in Nawalparasi West.

Of these, the 18-km section from the New Butwal Substation to the Nepal–India border was completed in September. That section forms the Nepali part of the New Butwal–Gorakhpur cross-border transmission line, but approvals and other steps are still needed before it can be energised.

Infrastructure for Domestic Use and Power Trade

MCA-Nepal said the network will expand Nepal's transmission capacity and help connect power from hydropower projects to the national grid. It will also provide infrastructure for domestic consumption of future generation and for cross-border electricity trade.

Electricity trade is among the main economic issues for Prime Minister Balendra Shah's visit to India on November 22-23. According to the Nepal Electricity Authority, Nepal exported electricity worth more than Rs 29.32 billion to India and Bangladesh in fiscal year 2082/83.

t
How are you feeling after reading this post?

Share

Comments

Comments

0 comments · join the conversation

No comments yet

Be the first to share your thoughts.