Rahughat 40 MW Hydropower Project Begins Commercial Generation a Decade and a Half After Construction Began
The project has a power purchase agreement with NEA to sell about 240.6 million units a year.
Kathmandu. The 40 MW Rahughat Hydropower Project in Myagdi, built by Raghuganga Hydropower Limited, a subsidiary of the Nepal Electricity Authority (NEA), has begun commercial generation. The project entered commercial operation after completing its test period, about a decade and a half after construction began, Raghuganga Hydropower managing director Ganesh KC said.
The project signed a power purchase agreement (PPA) with the NEA in 2019 (Chaitra 2075) to generate 240.59 million units a year. Its power is fed into the national grid through the Dana–Kushma 220 kV transmission line.
Flood Hit During Testing
Test generation began on September 22 (Asoj 6). But a Kali Gandaki flood on September 27 (Asoj 11) eroded and damaged the powerhouse area at Tilkenichaur in Raghuganga Rural Municipality-3, extending the test period.
From a Cancelled Contract to a Redesign
The NEA signed a Rs 2.5 billion civil contract with India's IVRCL in November 2010 (Kartik 18, 2067). Had the work gone to plan, the project would have started generating by 2013/14. With the contractor in financial trouble and work stalled, the NEA terminated the contract in 2015/16, when physical progress was only 12%.
The NEA then restructured the project, raising its capacity from 32 MW to 40 MW, and in 2016/17 set up Raghuganga Hydropower as a subsidiary to build it under a company model.
Indian EXIM Bank Loan
The project was built on an engineering, procurement and construction (EPC) basis with a $67 million concessional loan from India's EXIM Bank and investment from the NEA and the Government of Nepal.
The civil contract went to Indian firm Jaiprakash Associates (JP) for about Rs 6 billion in November 2017, with a 45-month completion target. State-owned Bharat Heavy Electricals Limited (BHEL) signed the electromechanical contract for about $10.29 million in late 2019. The project deadline was extended four times.
The dam sits at Dagnam and Jhinko Phedi in Raghuganga Rural Municipality-4 and 5. A 6.27 km headrace tunnel, broken through in July 2024, carries water to the powerhouse at Tilkenichaur beside the Beni–Jomsom road.
Comments
0 comments · join the conversation
No comments yet
Be the first to share your thoughts.
Add a comment
Your comment will appear after a quick review.
Comment submitted
Thanks! Your comment is in the moderation queue and will appear after verification.
Reply to comment
0 replies
Reply submitted
Thanks! Your reply is in the moderation queue and will appear after verification.